Blower installation – Day 1

Having travelled to Ormskirk from Poole, Martin Legg and his team arrived, ready for the task of dismantling and removing the old blowing plant, running cabling for the new switchgear and installing the new starter, preparing for installation and commissioning on Day 2.

The afternoon was spent dismantling the 1927 blowers, which was a task in itself!  The photograph below shows the process partially completed; the blowers are disconnected and the motor and starter have been removed; the blowers themselves, however, remain in situ.

IMG_2496

6:00pm saw the road closure in place, with traffic lights restricting the flow on the A570 past the church wall; here, we can see just how little room there is for manoeuvre.

IMG_2524

IMG_2511

All the movement of equipment had to take place through the door leading straight onto the carriageway; this leads down a tunnel under the churchyard to the blowing chamber beyond:

IMG_2516

A mobile crane had to be used to take the weight of the new blower, which finally arrived in its new home:

IMG_2515

IMG_2521

All is now set for Day 2!

 

 

 

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s